The KYN28-12 MV Cubicle is an indoor metal-enclosed, withdrawable medium-voltage switchgear cubicle for three-phase AC power distribution and control at 50 Hz.
Send Inquiry
Description
Technical Parameters

The KYN28-12 MV Cubicle is an indoor metal-enclosed, withdrawable medium-voltage switchgear cubicle for three-phase AC power distribution and control at 50 Hz.

 

Technical Specifications

 

Parameter

Specification

Product Type

Indoor withdrawable metal-enclosed MV Cubicle

Model

KYN28-12

Rated Voltage

3 kV, 6 kV, 10 kV; 12 kV class*

Rated Frequency

50 Hz

Rated Current

630 A, 1000 A, 1250 A, 1600 A, 2000 A, 2500 A, 3150 A

Rated Short-Time Withstand Current

20 kA, 25 kA, 31.5 kA, 40 kA

Rated Short-Circuit Duration

4 s

Rated Peak Withstand Current

50 kA, 63 kA, 80 kA, 100 kA

Power-Frequency Withstand Voltage

42 kV / 1 min between phases and phase-to-ground; 48 kV / 1 min across open contacts

Lightning Impulse Withstand Voltage

75 kV between phases and phase-to-ground; 85 kV across open contacts

Enclosure Protection

IP4X

Internal Compartment Protection

IP2X

Main Switching Device

Withdrawable vacuum circuit breaker

 

Inside the MV Cubicle


The KYN28-12 divides the primary and secondary equipment into separate compartments, with each compartment assigned a defined electrical or mechanical function.


Busbar Compartment
Houses the main and branch busbars in the upper section of the cubicle. Insulating supports maintain the required electrical separation between the busbar system and the enclosure.


Circuit Breaker Compartment
Accommodates the withdrawable vacuum circuit breaker and truck mechanism. The compartment provides the guide and operating structure required for breaker movement.


Cable Compartment
Provides the termination area for incoming or outgoing cables. Depending on the circuit arrangement, it also accommodates primary components such as CTs and the earthing switch.


Relay & Control Compartment
Contains protection, measurement, control, indication and auxiliary equipment associated with the secondary circuit.


Enclosure
The cabinet body and partition panels are formed from aluminum-zinc coated steel sheets processed by CNC machining and multi-bending. Bolted connections are used for enclosure assembly, while cabinet doors receive electrostatic powder coating.

 

Configuration from the Single-Line Diagram


The KYN28-12 lineup is arranged according to the electrical functions shown on the project single-line diagram (SLD). The SLD identifies the position of each cubicle in the distribution system and shows its connection to the incoming source, busbar, transformer, outgoing circuit or bus-section arrangement.


Typical cubicle functions shown on the SLD include:
Incoming Feeder: Connects the upstream power source to the MV busbar.


Outgoing Feeder: Connects the MV busbar to a downstream distribution circuit.


Transformer Feeder: Connects the MV busbar to a transformer circuit.


Voltage Transformer Section: Provides the VT connection shown in the voltage measurement or protection scheme.


Metering Section: Accommodates the measurement arrangement specified in the metering scheme.


Bus Section / Coupling Section: Provides the switching connection between separate busbar sections.


The SLD assigns each cubicle its electrical function and establishes the sequence and connection relationship of the lineup before the primary and secondary arrangement is finalized.

 

IMG2155

 

What Determines the MV Cubicle Configuration?


The configuration is finalized around five areas:


Electrical duty: Voltage, continuous current and short-circuit duty establish the required electrical ratings.


Primary equipment: The selected circuit breaker, CTs, VTs and earthing arrangement determine the primary circuit layout.


Secondary scheme: Protection, measurement, control and auxiliary circuits determine the relay/control equipment and wiring arrangement.


Cable connection: Cable quantity, termination arrangement and connection direction affect the cable compartment layout.


Operating arrangement: The required switching and interlocking sequence determines the associated operating mechanisms and control functions.


The final arrangement is checked against the approved project drawings and technical specification before production.

 

Mechanical Interlocking & Grounding


The withdrawable vacuum circuit breaker moves between the service and test/disconnected positions within the circuit breaker compartment.


Mechanical interlocking controls the truck movement and prevents operation when the defined position conditions are not met.


When the breaker is withdrawn, the shutter covers the primary contact area. The breaker position can be observed through the monitoring window without opening the cabinet door.


The cubicle connects to the main grounding busbar. Where specified, the earthing switch is integrated into the primary circuit and grounding arrangement.


Project-specific interlocking sequences are defined in the approved electrical and control documentation.

 

IMG2161

 

How We Build an MV Cubicle


Worldwide Electric operates a manufacturing base exceeding 200,000 m², with more than 120 sets of production and testing equipment supporting its electrical and industrial production operations.


Cabinet Fabrication
Aluminum-zinc coated steel sheets are CNC-machined and multi-bent for the cabinet body and internal partition panels. The panels are assembled with bolted connections, forming the compartment structure before primary equipment is installed.


Busbar Processing
The main and branch copper busbars are prepared according to the specified current rating and cabinet arrangement. Busbar sections are assembled with the corresponding branch conductors and insulating supports before the primary circuit is completed.


Primary Equipment Assembly
The withdrawable vacuum circuit breaker, static contact assembly, current transformers, earthing switch and other specified primary components are installed according to the approved circuit arrangement.


Secondary Wiring
Protection, measurement, control and auxiliary circuits are wired against the approved secondary drawings. Terminal identification and circuit connections are checked against the specified control and protection scheme.


Grounding Assembly
The grounding busbar runs through the cubicle arrangement and connects the cabinet grounding points. Where an earthing switch is specified, its grounding connection is connected to the main grounding busbar as part of the completed grounding circuit.


Final Assembly
The withdrawable mechanism, operating components, cabinet doors, secondary connections, grounding connections and specified accessories are fitted after the enclosure and primary circuit assemblies are completed.

 

Quality Inspection


The completed KYN28-12 is inspected against the approved drawings, secondary wiring diagrams and specified electrical requirements before shipment.


Dimensional Check
Cabinet dimensions, compartment interfaces and component mounting positions are checked against the approved drawings.


Wiring Check
Terminal connections, wire identification and circuit continuity are checked against the secondary wiring diagrams.


Electrical Check
Specified insulation, dielectric and circuit-related tests are performed according to the confirmed product configuration and applicable test requirements.


Mechanical Check
Circuit breaker withdrawal, service and test/disconnected positions, earthing switch operation and related mechanisms are checked through their defined operating sequences.


Final Check
The completed cubicle is checked for component completeness, labels, grounding connections, accessories and required documentation before shipment.

 

product-1170-891

 

FAQ

 

Q: Can a specific vacuum circuit breaker brand or model be specified?

A: Yes. The required breaker can be specified during technical clarification. Rated current, breaking capacity, control requirements and mechanical interface are confirmed before configuration approval.

Q: Do you provide MV Cubicle drawing and design services?

A: Yes. Technical drawings can be prepared from the customer's electrical requirements and project drawings. The required drawing scope is confirmed before design work begins.

Q: Can project-specific documentation requirements be accommodated?

A: Yes. The document package can be defined according to the project submission requirements, including technical specifications, general arrangement drawings, circuit diagrams, component lists and inspection documentation where required.

Q: Which standards can be specified for the KYN28-12 MV Cubicle?

A: The applicable design and testing standards should be stated in the project specification or RFQ. The required standard basis is confirmed during technical clarification before the technical proposal is finalized.

Q: Can the KYN28-12 be supplied with a project-specific control voltage?

A: Yes. The control voltage can be specified according to the project secondary circuit requirements. The required voltage is confirmed during technical clarification and reflected in the approved secondary drawings before production.

Q: How do I request a quotation for an MV Cubicle?

A: Send the single-line diagram, electrical specifications, required cubicle quantity and project requirements. The configuration is reviewed before the quotation is prepared.

Q: What is the payment term for an MV Cubicle order?

A: The standard payment term is 30% advance payment and 70% before shipment. Project-specific terms can be discussed during order negotiation.

Q: Do you provide technical support after delivery?

A: Yes. Technical support covers commissioning and maintenance-related issues after delivery. A 24-hour service and complaint hotline is provided for customer support.